# |
Title |
Description |
Examples |
Attachments |
1 |
Hot Work |
A Hot Work is a work with a potential source of ignition or if it may produce a possible source of ignition.
Exemption: Hotwork in Welding Shop |
- Grinding;
- Chipping;
- Cutting;
- Welding;
- Burning;
- Temporary use of internal combustion engines and non-intrinsically safe (IS) equipment in Zones I or 2;
|
- Risk Assessment;
- TBT;
- Fire Warden Checklist (on PTW);
|
2 |
Work at Height |
Working above 2 m where fixed or temporary guarding is not provided is considered as Work at Height.
Exemption: Derrickman racking pipes on Monkeyboard level |
- Manriding Activities by Winch, Crane or Telehandler;
- Erecting or dismantling scaffolding;
- Greasing on Crown block;
- Dismantling/Removing of handrails, ladders, grating (rigging down and rigging up);
|
Depending on the Ops nature:
- F-24 – Pre-Manriding Checklist;
- F-79 – Crane Manbasket Checklist;
- Scaffolding checklist (by 3rd Party);
|
3 |
Works with Dangerous Substances |
Work with substances hazardous for health |
- Handling Radioactives;
- Handling Explosives;
- Handling Chemicals that cannot be identified;
- Handling Chemicals that doesn’t have MSDS;
- Handling NORM contaminated equipment;
- Handling/Pumping Acid;
|
- Risk Assessment;
- TBT;
- F-25 – Radio Silence Checklist;
- Explosives Checklist (by 3rd party);
|
4 |
Pressure Testing |
Pressure testing of equipment, piping systems or hoses according to relevant procedures. |
Pressure test of any units/equipment, e.g.:
- Cement Unit;
- BOP;
- Test manifold;
- Choke manifold;
- Pressure lines;
- Pressure vessels;
- Well head;
- Silo;
- etc.
|
|
5 |
Confined Space Entry |
A confined space is any area with limited or restricted means for entry or exit and is not designed for continuous occupancy. |
- Cellar;
- Mud Tanks;
- Sewage tanks;
- Water tanks;
- Silos;
- Hydrocarbon tanks;
|
- Risk Assessment;
- TBT;
- Confined Space Entry Checklist (on PTW);
- F-11 – Confined Space Monitoring Sheet;
- Isolation Certificate;
|
6 |
Well Operation/Well Intervention |
Operations involving third party and unit own activities posing combination of multiple hazards. |
- Well stimulation;
- Coiled tubing operation;
- Setting plug in or removal of X-mass tree.;
- Well testing activities, flow tests in particular;
- All Third Party activities related to well, e.g.:
- Installation of any third party equipment
- Rigging up packer/larleur equipment;
- Cementing and associated activities;
- Wireline operation/production logging;
- Pressure cleaning of tubulars by contractor;
|
- Risk Assessment;
- TBT;
- F-39 – 3rd Party Equipment;
|
7 |
Isolation of Safety System |
Work that involves isolation and testing or bypassing of safety systems.
For detailed listing of safety systems refer to HSE Case |
Work on any Safety Critical Equipment while drilling or workover:
- Emergency shutdown systems
- Firefighting systems
- Pressure Relief systems
- Detection systems
- Alarm systems
- Emergency power and non-interruptible power supply
- BOP and diverter systems
- Accumulators Unit maintenance during operations.
- Crown-o-Matic
- Floor-o-Matic
- Any other system designed or used to form a safety barrier.
|
- Risk Assessment;
- TBT;
- Isolation Certificate;
|
8 |
Lifting |
Non-routine Lifting Activities |
- Lifting Personnel;
- Lifting more than 5t;
- Tandem Lifting;
- Lifting items over pressurized equipment such as producing wells, or pressure vessels;
|
- Risk Assessment;
- TBT;
- F-59 – Lifting Plan;
|
9 |
Maintenance
|
Preventive and Troubleshooting Maintenance Activities |
- Working on equipment that has auto or remote start functions;
- Non-routine maintenance in mast during normal operations;
- Working on equipment requiring any kind of isolation, either mechanical or electrical, e.g.
- Changing liners on MPs
- Draworks maintenace
- Elmago maintenance
|
- Risk Assessment;
- TBT;
- Isolation Certificate;
|
10 |
Other |
Any operation that may pose a hazard due to its nature, or due to lack of safety barriers. |
- Opening various valves that might lead to a spill of hazardous substances to the nature;
- Excavation on location while Unit is operating;
- Work above or around water tanks or pits;
- Erecting or moving equipment in close proximity to overhead power lines;
- Use of high pressure jetting equipment (>2000psi)
- Slip & Cut
- Re-charging of Nitrogen Bottles;
- Grit blasting;
|
- Risk Assessment;
- TBT;
- Isolation Certificate;
- F-39 – 3rd Party Equipment;
|
Faisal for Category 6:
*N/U/N/D BOP
*R/U,R/D BOP
*Raisup and lower mast
*mud pump repaire
*Acid job
*Cement job
*Curing job
*Slip and cut drill line
*TDS service
*Draw work service
*Engine service
*any third party job